Legislation Details

File #: R2025-048    Version: 1
Type: Resolution Status: Consent Agenda
File created: 11/26/2024 In control: City Council
On agenda: 3/18/2025 Final action:
Title: Consider approving Resolution No. 2025-048 authorizing an Interlocal Agreement between the City of Farmers Branch, the Town of Addison, the City of Coppell, the City of Carrollton, and the North Texas Emergency Communication Center (NTECC) relating to funding of a new NTECC consolidated public safety communications center.
Attachments: 1. Resolution No. 2025-048, 2. Interlocal Cooperation Agreement - Design and Construction, 3. Presentation
Date Ver.Action ByActionResultAction DetailsPacketVideo
No records to display.
Title
Consider approving Resolution No. 2025-048 authorizing an Interlocal Agreement between the City of Farmers Branch, the Town of Addison, the City of Coppell, the City of Carrollton, and the North Texas Emergency Communication Center (NTECC) relating to funding of a new NTECC consolidated public safety communications center.

Body
REQUESTOR:
City Manager's Office

BACKGROUND:
In 2014, the Cities of Farmers Branch, Coppell, Carrollton, and the Town of Addison created a shared emergency communications center, the North Texas Emergency Communication Center (NTECC). The facility operates from a leased space of 11,800 square feet, with the initial lease term ending in April 2029. However, the existing space was insufficient for the center's growing needs over time. As a result, the expansion of the existing facility to the second floor was discussed. However, expanding upstairs and annual lease escalations are cost-prohibitive compared to buying and building a facility.

DISCUSSION:
In early 2023, the Cities started discussing plans for NTECC expansion to accommodate long-term needs. As a result, a needs assessment was conducted, which revealed that more space is needed to meet the cities' growing needs. Additionally, cost analysis revealed that a new building would reduce costs by over $24 million over a 30-year term.

The estimated cost of the proposed construction of the new NTECC building is $22.263 million. Farmers Branch's share of the cost is $5 million. The City of Farmers Branch, through Certificate of Obligation (Cos) Bonds, has allocated $5 million for NTECC. This Certificate of Obligation Bonds was approved as part of the FY 2024-25 budget process (Ordinance No. 3887) to pay for designing, constructing, renovating, improving, and equipping a public safety communication facility and dispatch center and acquiring land.
The first interlocal agreement to purchase the land to construct the new NTECC building was approved during the October 17, 2024, Ci...