Title: Consider approving Resolution No. 2025-072 authorizing the City Manager to execute a contract with J & L Construction, LLC, for the 2025 Water Main Replacement project in the amount of $3,218,551; and take appropriate action.
Attachments: 1. Resolution No. 2025-072, 2. Contract, 3. Bid Tab, 4. Construction Notice Memorandum, 5. Site Map, 6. Presentation
Date Ver.Action ByActionResultAction DetailsPacketVideo
No records to display.

Title

Consider approving Resolution No. 2025-072 authorizing the City Manager to execute a contract with J & L Construction, LLC, for the 2025 Water Main Replacement project in the amount of $3,218,551; and take appropriate action.

 

Body

REQUESTER:

Public Works Department

 

BACKGROUND:

Public Works staff have identified drinking water system improvements for each year as part of the continual evaluation and maintenance of the system. The project focuses on older cast-iron water mains installed in the 1950s and 1960s. Approximately 9,225 linear feet of cast iron water main will be replaced with new PVC lines. The estimated construction timeline is 6 months to complete the entire project. Once the project is awarded to the Contractor, they will develop a timeline for each waterline section. The 2025 Water Main Replacement will be in the following areas:

•                     Longmeade Drive from Rawhide Parkway to Webb Chapel Road

•                     Wood Manor Circle from Farmers Branch Lane to 12311 Wood Manor Circle

•                     Ford Road from Farmers Branch Lane to Leta Mae Lane

•                     Villa Creek Drive from 2775 Villa Creek Drive to Josey Lane

•                     Valley View Lane from Webb Chapel Road to Belfield Drive

•                     Sunbeck Circle from Josey Lane to Josey Lane

•                     Chapelview Drive from Westminster Drive to Veronica Road

•                     Reedcroft Drive from Bay Meadows Circle to Josey Lane

 

DISCUSSION:

The Engineer’s Opinion of Probable Construction Cost (OPCC) for this project is $3,666,000. On April 21, 2025, the city received seven bids for the construction of this project. J & L Construction, LLC submitted the lowest bid, meeting all requirements, in the amount of $3,218,551. When Construction of this project begins, residents along those streets will receive construction notices when contractor crews are working in their area.

 

The seven received bids were:

1.                     J & L Construction, LLC in the amount of $3,218,552

2.                     Aushill Construction, LLC in the amount of $3,345,510

3.                     2R Construction Services in the amount of $3,481,125

4.                     Jeske Construction Company in the amount of $3,628,959

5.                     SYB Construction Company in the amount of $3,795,803

6.                     S-Co Incorporated in the amount of $3,953,998

7.                     Excel 4 Construction, LLC in the amount of $4,014,530

 

FISCAL IMPACT:

The project cost of $3,218,551 will be funded through the Capital Improvement Utility Non-Bond Fund. There are sufficient funds in the fund balance, but it is not budgeted in the non-bond CIP. However, a fund transfer will be required to replenish the account to cover the project expense.

 

DISTRICT:

Districts 4 and 5

 

POSSIBLE COUNCIL ACTION:

1. I move to approve Resolution No. 2025-072 as presented.

2. I move to approve Resolution No. 2025-072 with modifications.

3. I move to table the issue for further study or take no action.

 

ATTACHMENT(S):

1.                     Resolution No. 2025-072

2.                     Contract

3.                     Bid Tab

4.                     Construction Notice Memorandum

5.                     Site Map

6.                     Presentation