Skip to main content
File #: R2017-121    Version: 1
Type: Resolution Status: Regular Agenda
File created: 10/24/2017 In control: City Council
On agenda: 11/14/2017 Final action:
Title: Consider approving Resolution No. 2017-121 authorizing the purchase and installation of replacement athletic field LED lights at Oran Good Park Field 4 from Groves Electrical Services, Inc. through the Buy Board Purchasing Cooperative agreement; and take appropriate action.
Sponsors: Jeff Harting
Attachments: 1. Resolution No. 2017-121, 2. Site Location
Date Ver.Action ByActionResultAction DetailsPacketVideo
No records to display.

Title

Consider approving Resolution No. 2017-121 authorizing the purchase and installation of replacement athletic field LED lights at Oran Good Park Field 4 from Groves Electrical Services, Inc. through the Buy Board Purchasing Cooperative agreement; and take appropriate action.

 

Body

BACKGROUND:

The City’s athletic field light poles are in excess of 30 years old.  Following an engineer’s 2014 assessment of the system, 21 of 107 poles were identified as having a service life of five years or less with the remainder having a service life of five to fifteen years.   Based on this study a plan was put in place, beginning with the 14/15 mid-year budget, to allocate $225,000 per year in the Non Bond CIP for 15 years to achieve total replacement of poles, lights, wiring, and control systems.  That plan was based on currently available and affordable technology, metal halide lights that are High Intensity Discharge (HID).  HID was said to be readily available for installation for the foreseeable future.  Light Emitting Diodes (LED), though more efficient, was also much more expensive and not typically used in municipal settings.

 

To date, the entire system at Cox Park has been replaced with HID.

 

In the last two years there have been many lighting technology changes.  While the City has a 25 year maintenance agreement on Cox Park, HID lights will not be produced by this manufacturer beyond the next, approximately, three years.  Technology has changed bringing the cost down on LED making it more affordable, though still more than HID.

 

DISCUSSION:

LED systems are much more energy efficient, using approximately 58% less electricity than existing HID.   Replacing the system on Oran Good 4 with HID would cost $260,871 while replacing with LED will cost $285,591.   Oran Good 4 with HID would cost approximately $2,670 to operate annually while LED would cost approximately $1,120 to operate annually.   The recommendation is to switch to LED for this and future portions of this project. 

 

Going forward with LED will require either a replacement schedule cascading beyond the advised 15 years or increasing the annual allocation in Non Bond CIP from $225,000 to $300,000 beginning with the 2018/19 budget.   Current project completion is projected to be 2029/30.

 

The contractor for this project is Groves Electrical Services, Inc., a Farmers Branch business that has been installing and maintaining sports field lighting for many years.  Groves has a long and positive history of working on City projects. 

 

The cost for this year’s replacement is Buy Board Priced not to exceed $285,591.  There is a total of $352,023 available in the Non Bond CIP budget for this project. 

 

POSSIBLE COUNCIL ACTION:

1.                     I move to approve Resolution No. 2017-121 authorizing the purchase and installation of replacement athletic field lights at Oran Good Park field 4 from Groves Electrical Service, Inc.

2.                     I move to approve Resolution No. 2017-121 authorizing the purchase and installation of replacement athletic field lights at Oran Good Park field 4 from Groves Electrical Service, Inc. with modifications.

3.                     I move to table the issue for further study or take no action.

 

ATTACHMENTS:

1.                     Resolution No. 2017-121

2.                     Site Location