BACKGROUND:
The FY2018-19 Fixed Asset Fund for vehicle/equipment replacement includes the replacement of the Justice Center generator. The generator is 28 years old, which meets the recommended generator replacement criteria to ensure future generator reliability during outages and supports Critical Business Outcome - Plan for, build, and maintain high quality public assets.
DISCUSSION:
The City of Farmers Branch requested a quotation from the HGAC Contract. City Administration evaluated the quotation as to meeting specifications and desire to award the purchase of the replacement generator to Loftin Equipment Company.
The FY2018-19 budget amount for the replacement generator is $120,000. The remaining $36,022 will be used for a contractor to remove the old generator as well as install the new generator. Administration is anticipating the entire project to be less than the budgeted amount.
FISCAL IMPACT:
Budgeted Financial Impact of $83,978 from account number
RECOMMENDATION:
City Administration recommends to approve the purchase of a replacement generator for the Justice Center from Loftin Equipment Company through the HGAC Contract budgeted in the FY2018-19 Budget.
POSSIBLE COUNCIL ACTION:
1. I move to approve Resolution 2019-67 authorizing the City Manager to approve the purchase of a replacement generator for the Justice Center in the total amount of $83,978.
2. I move to approve Resolution 2019-67 authorizing the City Manager to approve the purchase of a replacement generator for the Justice Center in the total amount of $83,978, with modifications.
3. I move to table the issue for further study or take no action.