File #: R2022-005    Version: 1
Type: Resolution Status: Consent Agenda
File created: 12/15/2021 In control: City Council
On agenda: 1/4/2022 Final action:
Title: Consider approving Resolution No. 2022-005 authorizing an agreement with Nathan D Maier Consulting Engineers, Inc. for professional design services of the FB Creek Erosion Control Reach 4 Project; and take appropriate action
Attachments: 1. Resolution No. 2022-005, 2. Professional Services Agreement, 3. Location Map, 4. Form 1295
Date Ver.Action ByActionResultAction DetailsPacketVideo
No records to display.

Title

Consider approving Resolution No. 2022-005 authorizing an agreement with Nathan D Maier Consulting Engineers, Inc. for professional design services of the FB Creek Erosion Control Reach 4 Project; and take appropriate action

 

Body

BACKGROUND:

On June 19, 2018 Freese and Nichols presented to Council during Study Session, a project prioritization list for Farmers Branch Creek that was established during the creek study.  From this list, there were projects identified requiring erosion repair work. Based on the need to make these repairs in order to stabilize the overall creek, City Council directed staff to move forward with the design and subsequent construction for the erosion repair projects based on a reach concept.  Staff was to group projects within a given reach of the creek that affected multiple properties

 

DISCUSSION:

The City has negotiated a professional services agreement with Nathan D Maier Consulting Engineers, Inc. for the design of improvements identified as Reach 4 which is a portion of Project ID: Area 2 as presented by the Freese & Nichols CIP Prioritization Project List located upstream of Josey Lane Bridge and downstream from Veronica Road.

 

DISTRICT:

District 3 (Williams)

 

FISCAL IMPACT:

Budgeted Financial Impact ($181,600 from the Storm Water CIP Fund)

 

RECOMMENDATION:

City Administration recommends approving Resolution No. 2022-005 authorizing an agreement with Nathan D Maier Consulting Engineers, Inc. for professional, design services of the FB Creek Erosion Control Reach 4 Project in the amount of $181,600.

 

POSSIBLE COUNCIL ACTION:

1. I move to approve Resolution No. 2022-005

2. I move to approve Resolution No. 2022-005 with modifications.

3. I move to table the issue for further study or take no action.

 

ATTACHMENT(S):

1.                     Resolution No. 2022-005

2.                     Professional Services Agreement

3.                     Location Map

4.                     Form 1295