Title: Discuss the traffic control plan for the southbound Marsh Lane bridge project.
Sponsors: Randy Walhood, Public Works Director
Attachments: 1. Traffic Control Plan
Related files: R2014-112
Date Ver.Action ByActionResultAction DetailsPacketVideo
No records to display.

Title

Discuss the traffic control plan for the southbound Marsh Lane bridge project.

 

Body

BACKGROUND:

Council Member Bomgardner requested that City Administration present the traffic control plans for the pending reconstruction of the southbound Marsh Lane Bridge.

 

Dallas County is preparing to advertise the project in March, which would put construction beginning approximately in June 2016. 

 

The perspective low bidder would have input on the traffic control plan which would be coordinated with the City and Dallas County.  Dallas County will be administrating the construction contract.  As with any detour, adjustments will be made after implementation to make traffic flow as efficiently as possible.

 

There have been two public meetings on this project held at the Recreation Center on February 16, 2015 and August 19, 2015.

 

ATTACHMENT:

1.                     Traffic Control Plan